Technical Report

Malecon 2000 Project; Malecon Gardens (Northern Sector) Malecon 2000 Foundation

General Manager: Dr. Pedro Gomez-Centurion
Project Director of: Mr. Guillermo Suaya
Technical Manager: Roberto Espíndola, Engineer

Authors

Design Team Chief: Douglas Dreher A., Architect
Urban-architectural consultant: Oxford Brookes University / UK; Tito Fernandez Davila, Architect; Noé Carvajal, Architect
Urban Furniture Design: Luz Marina Salgado, Designer
Design Development: Angela Saa, Architect; Julio Marcillo, Architect Sergio Alvarado, Architect; Janio Moran, Architect; Daniel Wong, Architect; Antonella Rossi, Architect

Collaborators

Landscape Design: Cecilia Von Buchwald, Landscaper
Sanitary Design: Feliciano Gonzales, Engineer
Electric Design: José Hill, Engineer
Structure Design: Carlos Chon, Engineer
Fountains Hydraulic Design: Pablo Donoso, Engineer
Metal mechanics Consultant: Carlos Ordonez, Engineer

Surface

22,000 m2

Project Date

2001

Inauguration Date

October 30, 2001

Cost of the work

$22'000,000

Pictures

Carlos Rodríguez S., Photographer